Anhui a customer 66 tons of white glass electric melting furnace successfully put into operation
+
  • Anhui a customer 66 tons of white glass electric melting furnace successfully put into operation

Anhui a customer 66 tons of white glass electric melting furnace successfully put into operation

Classification:

Engineering case

Keywords:


        5Month7Day, a customer in Anhui66Tons of fine white glass electric melting furnace restart expansion project smooth ignition,5Month24Daily on-time discharge and production. The rated production capacity is reached in about one week after discharge.95%, the material has reached the agreed standards of both parties, melting unit consumption.1.0-1.05KWHThe customer is very satisfied. This electric stove is my company2023The 27th electric furnace successfully put into operation in the year.

(The rated production capacity is reached about a week after discharge.95%。)

The customer is a large factory with a certain scale of production of daily utensils, there are currently two large pool furnace. It is planned to fill the gap in the high-end market by introducing electric furnaces to improve product quality. Because of the outbreak, the furnace was temporarily discontinued after the first start-up of the operation for half a year, this start-up customer requirements for daily melting capacity from60tons expanded66Tons. In order to meet the urgent requirements of customers, in line with the principle of minimizing changes and minimum investment under the existing conditions, after careful demonstration and careful design, the melting area of the kiln is determined to be unchanged, and the number and insertion position of the main melting electrode are increased. The client has an efficient working team, from the identification of the solution to the smooth commissioning of the project.2Months of time, created a model of efficient cooperation.

The smooth commissioning of this electric furnace gives customers a lot of confidence. It is reported that the decision-makers are already planning the second phase of the project to further accelerate the pace of furnace electrification.

(The quality inspection personnel are very excited after seeing the crystal clear products)