Nissan 21 flat soda-lime glass electric melting furnace project successfully ignited and discharging
+
  • Nissan 21 flat soda-lime glass electric melting furnace project successfully ignited and discharging

Nissan 21 flat soda-lime glass electric melting furnace project successfully ignited and discharging

Classification:

Engineering case

Keywords:


Our company for a factory in Shandong Nissan21Flat soda-lime glass electric melting furnace new project in2023Year5Monthly smooth production.This is the 22nd electric furnace that our company overhauled and put into production in 2023,The product of this project is a product whose demand is gradually increasing in the current market. Whether it is on the production date or the product quality requirements are extremely high, it will be put into operation on the third day after it is put into production. The later product market is gradually expanding, and technological improvement and upgrading are also in progress. Orderly progress.