A company in Nantong successfully put into operation 3 ㎡ electric melting furnace overhaul
+
  • A company in Nantong successfully put into operation 3 ㎡ electric melting furnace overhaul

A company in Nantong successfully put into operation 3 ㎡ electric melting furnace overhaul

Classification:

Engineering case

Keywords:


Our company reformed and restarted a 9.5 ㎡ electric furnace for a company in Nantong. It was successfully ignited and heated on April 1, 2023, and was successfully discharging on April 14. This is the 21st electric furnace overhauled and put into production by our company in 2023. The material quality reached the normal production standard 5 days after discharging.

 

This project is a renovation and restart project. The customer's original electric furnace produced high boron material products, which have been suspended for four and a half years. The external steel structure of the kiln, automatic feeding machine, electrical control system, etc. are seriously eroded and aged. According to the customer's request, our company reformed and restarted all equipment structures of its kiln to produce sodium calcium high white material products.

 

During the construction and installation process, the customer's order was relatively urgent and the construction time was limited. The on-site personnel reasonably arranged the construction schedule, adjusted the construction time, and ensured the construction quality and efficiency. At the same time, they also received the active cooperation and strong support of the customers. The smooth commissioning of the project has been recognized by the customers and further promoted the close cooperation between the two parties, at the same time, it promoted the signing intention of the customer's discontinued pool furnace to electric furnace project.