Nanjing 1.5 Tons Furnace Successfully Put Into Operation
+
  • Nanjing 1.5 Tons Furnace Successfully Put Into Operation

Nanjing 1.5 Tons Furnace Successfully Put Into Operation

Classification:

Engineering case

Keywords:


During the post-Spring Festival epidemic this year, the Nanjing project identified a temporary overhaul.1.5Ton furnace, according to orders and market conditions, customer requirements50Day delivery,15Day ignition. Faced with the problem of the general extension of the delivery period of corundum bricks in China, the company has made concerted efforts to shorten the construction period in terms of design, procurement and production, and to work overtime in on-site construction, thus realizing the goal50Day delivery,13Day ignition, beyond customer expectations. The electric furnace is2021Our company was built and put into production in87Taichung furnace.