Huaian 8-ton bottle gallbladder project put into operation smoothly
+
  • Huaian 8-ton bottle gallbladder project put into operation smoothly

Huaian 8-ton bottle gallbladder project put into operation smoothly

Classification:

Engineering case

Keywords:


Jiangsu Huaian NissanThe 8-ton thermos glass electric melting furnace project started on April 16, 2019, with ignition conditions on May 20, ignition and heating on June 1, discharge and commissioning on June 14, and normal production on June 16. The design of this project takes into account the electrical matching and process compatibility of switching between red bile and white bile formulations, which meets customer expectations.