Nissan 10 tons of soda-lime glass electric melting furnace overhaul smoothly put into operation
+
  • Nissan 10 tons of soda-lime glass electric melting furnace overhaul smoothly put into operation

Nissan 10 tons of soda-lime glass electric melting furnace overhaul smoothly put into operation

Classification:

Engineering case

Keywords:


February 29, 2020 15:00 A Factory in Jiangmen, Guangdongnissan10 tons soda lime glass electric melting furnaceStart warming normally, inIt was put into production smoothly at 8: 00 a.m. on March 10.

The project inEntered the site on December 25, 2019, due to environmental protection reasons, the customer rebuilt in the new plant, in response to the urgent production needs of customers, the company's engineering department coordinated, under the premise of ensuring quality, January 19, 2020 installed and with the ignition conditions, the customer is very satisfied.